Transit
Station Spacing Criteria
Click on
the following links to Download the
Transit Station
Spacing Analysis worksheet (presented in Microsoft Word format):
Blank
Worksheet
Sample Worksheet
Background
A particular neighborhood within the
Sacramento Regional Transit District (RT) desires a new light rail
station. The neighborhood is located between two existing stations
about one mile in each direction. As the analysis to determine the
feasibility of the new station began, it was difficult to find
quantifiable criteria for locating new stations used by other
transit agencies.
Regional Transit, in conjunction
with Parsons Brinkerhoff (PB), developed a process that helps
evaluate and quantify a potential site for a new station. The
two-tiered process first identifies fatal flaws and the overall
feasibility of the station. The second part of the evaluation
provides more detail as to the effectiveness, connectivity and
transit-orientated d evelopment opportunities of the potential
station site.
Benefit of Criteria
The value of this process is beneficial to
staff and decision-makers as it provides criteria that can
objectively assist staff and decision-makers when evaluating the
feasibility of a new station along a transit alignment. Although
this criterion was developed for light rail stations, it could also
be applied to Bus Rapid Transit or other types of stations (e.g.
ferry terminals).
The following criteria were
approved by the RT Board on April 24, 2006. This two-tiered
approach represents only guiding standards for consideration of
staff and decision-makers. Any of the listed criteria may be
superseded by circumstances of a particular site. A final decision
may require additional considerations such as environmental
clearance, funding, design development and other relative
information.
Station Spacing Evaluation
and Criteria
The first tier of analysis is an
evaluation of four criteria to assess the proposed station site’s
"feasibility" and level of responsiveness to the community in which
it is proposed. This is a "fatal flaw" analysis.
If the proposed station site
passes this first test, no fatal flaws are identified, and the Board
decides to move forward with further analysis, then the second tier
of criteria are applied to determine the further appropriateness of
the station proposal and assist in the guidance process.
Tier 1 -- Initial
Evaluation (Fatal Flaw Considerations)
The initial level of evaluation
consists of four criteria:
- Constructability
(including Safety)
–
This
criterion addresses whether the proposed station physically is
able to be constructed and can be done so and not adversely
affect the safety of the system or the user. The proposed
station site would need to meet Sacramento RT’s horizontal and
vertical design criteria to b e considered further and not pose a
safety problem that cannot be resolved. Assuming it does, RT
should also qualitatively assess the "feasibility" of bringing a
station site "on-line." Because each station is inherently
unique, some locations will be more problematic and disruptive
to existing light rail services to bring on-line, as compared to
other sites. Those sites which are more problematic to bring
on-line (but potentially still feasible) may have increased
capital costs associated with them.
- Ridership and Density
Guideline Considerations –
RT
would use "minimum guidelines" for station spacing that are
based upon forecasted ridership and/or density models at or
around proposed stations. This allows RT to make a simple
initial assessment of the potential feasibility of the proposed
station site.
A spreadsheet-based "Station
Spacing Analysis Tool" has been developed to evaluate a proposed
station site’s ridership potential and/or population and
employment density relative to the existing RT stations. The
Station Spacing Analysis Tool is used to estimate ridership
and/or density for the proposed station site. Inputs are derived
from verifiable geographic and modal (feeder bus and number of
park and ride spaces) data. The definition of the proposed
station site is based on a range of a combination of population
and employment density (calculated using GIS) within a ¼ to ½
-mile walk shed.
Using the Direct Ridership
Model (SACOG Direct Light Rail Transit Ridership Models,
Richard Lee, Ph.D., April 2004 modified by PB, November 2005),
as it has been refined by the consultant; forecasted
ridership is developed based on the proposed station’s
surrounding population and employment. Using the same data, a
second "model" calculates the "average density" around the
station. These models produce numeric results related to
ridership potential and average density.
The results are then compared
to a histogram of existing (2005) ridership and/or existing
(2000) population and employment density data, which are
presented descending order.
The minimum guideline for
further consideration of the placement of a proposed station
would require that the forecasted ridership and/or average
density fall within the third quartile or better of all existing
RT Stations.
In addition to the first two
"functional" criteria, two community-based criteria were
identified and requested by the RT Board to be included in the
first-tier analysis.
- Environmental Justice
– Consistent with federal and RT policy, an assessment of the
environmental justice issues would be undertaken. As a
qualitative assessment, the level of transit-dependent
population (as defined by median household income below the
poverty level and auto ownership) within a ¼ or ½-mile radius
(as determined by GIS application of most recent US Census
data). A station would score "Low" if the environmental justice
population comprises 10% or less of the population; a "Medium"
if the environmental justice population is between 10% and 30%
of the population; and a "High" if the environmental justice
population is greater than 30% of the population within the ¼ or
½-mile radius.
- Community/Neighborhood
Input –
Input from the community
at large as developed from any community meetings held, or
comments received from the public, neighborhood leaders or
decision-makers (especially from the immediate neighborhood(s))
would be determined and a qualitative documentation of the level
of support (or non-support) for the station would be documented
(including the source(s) of the comments.) "Low" support would
be just that; "Medium" support would be a mixture of favorable
and unfavorable support; and "High" support would be mostly
favorable support received from the public through various
means.
RT Staff would determine the
technical feasibility of the station and its ability to be
constructed and would also compile and document the necessary
community-based information as appropriate and available for the
candidate station. At the end of the Tier 1 evaluation, RT Staff
would bring the two sets of results, along with a staff
recommendation on the next action, to the RT Board for consideration
of the candidate station.
The combination of information
developed for the candidate station would result in one of the
following staff conclusions:
- The station may be technically feasible, may
be embraced by the community and/or may serve an identified
environmental justice population base.
- The station may not be technically
feasible or poses a safety concern, may not be embraced
by the community and/or may not serve an identified
environmental justice population base.
In reality, each station will have
some combination of these factors.
The information will be summarized
and presented so that the Board can determine as to whether move
forward with the additional Tier 2 screening analysis.
Second Tier –
Comparative Evaluation
Back to top
If the proposed station "meets"
the first-tier criteria for further consideration, a "second-tier"
set of criteria would be used to further assist in the guidance of
selecting future light rail stations. Seven criteria have been
identified and are recommended to be applied for further guidance.
Travel Time Effects of
Proposed Station
- As guidance, the effects on travel times
should be assessed. While it is recognized that any one
individual station might add minimal effects to the travel
times, the cumulative effects could become
significant over the long-term as stations are added to a line.
In order to respond to and
communicate this issue to policy-makers, the cumulative
effects of a station are considered along with any other
stations that have been previously added since the baseline
year. The baseline year is 2005. Thus, the existing travel times
for the Gold Line from Folsom to Saint Rose of Lima Park in 2005
is 50 minutes; and the end-to-end running time for the Blue Line
from Meadowview is 48 minutes. These travel times would serve as
the basis for comparison. Each new station that is added
would add additional travel time.
Minimum
Station Spacing
Back to top
- As guidance, a set of "minimum station
spacing" criteria would be applied:
- The minimum standard for "urban core",
"downtown" and/or "town center" stations will be spaced no
closer than four blocks; where the geographic area is
generally recognized by the community as such (the key
example would be "downtown Sacramento").
- "Mid-town stations" defined as an area of
general density similar to the neighborhood-stations in the
Sacramento "mid-town" area between downtown and 29th
Street or Alkali Flat (La Valentina) or Arden/Del Paso and
would be spaced approximately ½ mile.
- "Suburban stations" would be spaced
generally no closer than one mile. This is consistent with
the stations north of Swanston, east of 65th
Street until Rancho Cordova and then east of Mather Field,
and south of City College.
- "Ex-urban stations" are spaced no closer
than two miles. These are stretches of the light rail lines
where infill development has not occurred (yet) – thus there
is no activity or rationale for closer station spacing. The
only identified examples in the Sacramento RT system are
between Sunrise and Hazel and between Hazel and Iron Point
(presently).
Operations
and Cost
Back to top
- Operations Analysis
– A quantitative assessment of whether the proposed station can
be accommodated operationally. This would entail analysis using RAILSIM® V.7 (or similar software acceptable to RT) to determine
if there is sufficient schedule time in the system for the new
station, if the train "meets" are acceptable, etc. If
operationally achievable, additional system operations costs (if
any) would be identified in Criterion # 4 below. Based on the
Operational Analysis, a scoring of "Low" (Poor or Infeasible
operational ability such as additional delays for "train
meets"), "Medium" (can be accommodated without operational
impacts beyond the additional station time requirements, or
"High" (improves operations) would occur.
- Incremental Operational and Capital Cost to
RT – A quantitative estimate of the
cost of the station to RT that identifies the net
additional O&M and Capital Cost (annualized) to RT. Costs of
the station (O&M + Capital [annualized]) to RT would score a
"Low" if RT was anticipated to cover 60% to 100%; a "Medium" if
30% to 60%; and a "High" if 0% to 30% is to be paid by RT.
- Local Bus Network Benefits or Cost
– A qualitative or quantitative assessment of the effect on
existing bus services in the area. Does the proposed station
result in a net increase or decrease in bus operating costs – as
compared to the existing system? An increase in the bus
operating cost (by requiring a more roundabout or extended
feeder service) would result in a "Low" score; no change would
result in a "Medium" score; and a decreased cost of existing
services would result in a "High" score.
Cost/Benefit Consideration
Back to top
- Cost Benefit Consideration
– The initial cost estimate for the candidate station will have
been prepared by RT Staff in the Tier 2, Criterion #4. These
costs will be compared to the relative benefits the station is
anticipated to have. The benefits may include additional riders
anticipated (based on Tier 1, Criterion #2) and could be a
simple "annualized cost per new rider." Over time, a comparison
of candidate stations will provide a benchmark for what is
envisioned as an acceptable cost/benefit ratio.
Redevelopment (TOD) Potential
- Transit-Oriented Development (TOD) Potential
– A qualitative assessment of the potential for development or
redevelopment within the walk shed of the proposed station site
is recommended. A score of "Low" would be assigned if the
potential (as determined through discussions with Planning staff
or other documented means) is
low or non-existent. A "Medium"
score would be assigned if the potential exists and there is
documented interest, but would require re-zoning, preparation of
Specific Plan or other TOD-oriented actions to occur. A "High"
score would result from the station area being within a
designated redevelopment area and/or already planned for higher
density, transit oriented development to occur.
Click here for more
information and to sample RAILSIM®
Back to top
|