Dos Rios Light Rail Station
The future Dos Rios Light Rail Station is located on the Blue Line on North 12th Street between Richards Boulevard and Sunbeam Avenue in Sacramento.
Dos Rios Construction
The construction of the Dos Rios Light Rail Station began in November 2024. The station is located on the Blue Line on North 12th Street between Richards Boulevard and Sunbeam Avenue in Sacramento.
Why the Station Hasn’t Opened Yet
Although construction at the station is complete, SacRT is waiting for the testing verification report to be accepted by the California Public Utilities Commission (CPUC) before the station can open for passenger service. Once SacRT receives approval, we will announce the official opening date and begin preparing for service.
Thank you for your patience as we complete this last required step to safely open the station.
Road Closures November 18, 2024
As of Monday, November 18, 2024, Ahern Street and Sproule Avenue are closed. Only local property owners will have access during this two-year closure.
Road Closure Information:
- No left turn traffic from North 12th Street to Ahern Street or Sproule Avenue.
- No through traffic from Sproule Avenue to North 12th Street or Sunbeam Avenue.
- No through traffic from Sunbeam Avenue to Sproule Avenue.
Detour signs will route traffic to North B Street.
- November 2024: Ahern Street and Sproule Ave are closed. Only local property owners have access during this two-year closure.
- Late 2024 to Early 2025: Retaining wall construction completed at the Loaves and Fishes and Gerber Collision parking lot.
- Early November 2025: Light rail service disruption for tie-in work on the new outbound tracks.
- March 2026: Light Rail service disruption for tie-in work to the new inbound track.
- September 2026: Station construction completed.
- September 2026: Station public opening TBD.
Background :
Project Report:
- Station Alternatives Analysis – 2006
- Preliminary design – mid-2014 through 2015
- Environmental clearance for “Twin Rivers Transit-Oriented Development and Light Rail Station” – CEQA: 2017, “Dos Rios Light Rail Station” – NEPA: 2019
- Center for Public Interest Design (CPID) outreach and chosen design – 2018
Sign up to be on the Dos Rios Project mailing list here.